For an introduction to Advanced Scheduling, please visit the How to Understand Concepts within Advanced Scheduling page.

  1. Access the Activity Scheduler for the desired Activity and click the Duplicate button next to the event you want to duplicate.


The Operation buttons, including Duplicate, are only shown when at least one event has already been created within the Activity.

The Scheduling (Timeslots) screen appears with a drop-down for the duplicate event's start date and time.

  1. Set the duplicate event's start date and time.

The event duration to be duplicated is displayed below the Start of the event menu.


3. Click the Save button.

NOTE: If there is any scheduling conflict, a message informs you that the modifications were not saved, and a table appears with data about the overlapping event(s).


4. Change the Start of the event and click Save.